The Fowlerville School District proposed a bond to go to vote in May of 2018. They are using the money to improve many of the schools building. They are a focusing on repairs for “Boilers, classrooms, instructional technology, and athletic fields”, according to a report from WHMI. Yet, the biggest project was replacing the shingle roof on Kreeger Elementary that was long due for repair.
CEI started the project in the middle of May. It is their first shingle roof project in over 10 years, making this an exciting project. The job included a full shingle tear off and replacement, as well as an addition of custom ridge vents fabricated by CEI’s sheet metal shop. Kreeger is a good change and gives the crews something different to work on. In the last 4 weeks, CEI has completed about half the reroof. They are still pushing forward as we begin to craft the ridge vents. The project is set to be done by August.